Blog

Back
Lauri Tuominen

Sales and Marketing Director for Enviroburners Oy.

Lauri has been working for 10 years with Enviroburners. His responsibilities have developed throughout the years from project management to sales.

   -  Pulp & Paper

Enviroburners to supply burner system to new pulp mill in Brazil

Enviroburners to supply burner system to new pulp mill in Brazil

The burner system for the new recovery boiler to Horizonte 2 pulp mill, Brazil will be supplied as a subcontracting project for Andritz Oy. The contract includes delivery of twelve heavy fuel oil / natural gas start-up burners with capacity of 19 MW each, four heavy fuel oil load burners with capacity of 65 MW each, main CNCG (Non Condensable Gas) burner for the recovery boiler with capacity of 30 MW and back-up flare incinerator for CNCG- and DNCG-gases with capacity of 21 MW. Commissioning of the burner system is planned in 2017. 

In addition, Enviroburners is also supplying all the fuel oil, natural gas and methanol valve units.


Back
Read next ‹ Back